THE BUILDING OF Little Toot 4 |








|
Building of the house and cabin floor frames |

|
House and Instrument panel completed |
|
Aft end of engine box and mount for the towing post. |







|
Three more layers of lead per side, with a total of 70 kgs, to help keep the boat trimmed. Lazz access hatches cut and teak trims fitted. |




|
Visor completed, 2 layers of 5 mm and 1 of 6mm. |
|
Engine is now all bolted in and drive shaft fitted and completed. Frame is made to strengthen the towing post. |
|
We weighed the Tug earlier this week and we are up to 1060 kgs. Which is great and on target. |



|
Interior and exterior shelves fitted. The picture to the top left is the interior Port side shelf, the slot is for the drawer that will hold the gas cooker (For cups of tea and sausages). Bottom left picture is the exterior outboard sole, the piece of fiberglass tube is for the exhaust hose to travel under. |